InfraStruXure 20kW System
Installation, Operation,
and Maintenance
Vista de pagina 0
1 2 3 4 5 6 ... 91 92

Indice de contenidos

Pagina 1 - InfraStruXure 20kW System

InfraStruXure 20kW SystemInstallation, Operation,and Maintenance

Pagina 2

Safety: Warnings4 InfraStruXure 20kW System—Installation, Operation, and Maintenanceb. If not an Inherently Limited Power Source, voltage and energy a

Pagina 3 - Contents

InfraStruXure 20kW System—Installation, Operation, and Maintenance 5OverviewInfraStruXure 20kW System ComponentsFront viewPower cables—The cables pro

Pagina 4

Overview: InfraStruXure 20kW System Components6 InfraStruXure 20kW System—Installation, Operation, and MaintenanceFront view (interior)42-position ci

Pagina 5

Overview: InfraStruXure 20kW System ComponentsInfraStruXure 20kW System—Installation, Operation, and Maintenance 7Front view (lower interior)DC disco

Pagina 6

Overview: InfraStruXure 20kW System Components8 InfraStruXure 20kW System—Installation, Operation, and MaintenanceRear viewMaintenance bypass panel a

Pagina 7

Overview: InfraStruXure 20kW System ComponentsInfraStruXure 20kW System—Installation, Operation, and Maintenance 9Main input connection optionsMain i

Pagina 9 - Emergency Power Off (EPO)

InfraStruXure 20kW System—Installation, Operation, and Maintenance 11Site PlanningInfraStruXure 20kW SystemWeight/dimensionsEnsure that the floor and

Pagina 10 - Handling and transport

Site Planning: InfraStruXure 20kW System12 InfraStruXure 20kW System—Installation, Operation, and MaintenanceHeat outputConsider the heat dissipation

Pagina 11 - Overview

InfraStruXure 20kW System: Installation, Operation, and Maintenance 13InstallationOverviewBefore you beginUnpack the InfraStruXure 20kW System accordi

Pagina 13 - Front view (lower interior)

14 InfraStruXure 20kW System: Installation, Operation, and MaintenanceInstall the InfraStruXure 20kW SystemLevel the InfraStruXure 20kW SystemLeveling

Pagina 14 - Rear view

Installation: Install the InfraStruXure 20kW SystemInfraStruXure 20kW System: Installation, Operation, and Maintenance 15Ensure that all power is off1

Pagina 15 - Main input connection options

Installation: Install the InfraStruXure 20kW System16 InfraStruXure 20kW System: Installation, Operation, and MaintenanceConnect utility conductors to

Pagina 16

Installation: Install the InfraStruXure 20kW SystemInfraStruXure 20kW System: Installation, Operation, and Maintenance 172. Knock out the perforated h

Pagina 17 - Site Planning

Installation: Install the InfraStruXure 20kW System18 InfraStruXure 20kW System: Installation, Operation, and MaintenanceRun input conductors. Run fou

Pagina 18 - Heat output

Installation: Install the InfraStruXure 20kW SystemInfraStruXure 20kW System: Installation, Operation, and Maintenance 19Connect an Emergency Power Of

Pagina 19 - Installation

20 InfraStruXure 20kW System: Installation, Operation, and MaintenanceInstall Additional InfraStruXure ComponentsInstall Shielding Troughs, Shielding

Pagina 20

InfraStruXure 20kW System: Installation, Operation, and Maintenance 21Route and Attach Overhead WiringRoute and attach power cables to equipment racks

Pagina 21 - Ensure that all power is off

Installation: Route and Attach Overhead Wiring22 InfraStruXure 20kW System: Installation, Operation, and Maintenance– For dual-feed devices within a r

Pagina 22

Installation: Route and Attach Overhead WiringInfraStruXure 20kW System: Installation, Operation, and Maintenance 235. From each NetShelter VX Enclosu

Pagina 23

Contents InfraStruXure 20kW System—Installation, Operation, and Maintenance iSafety ...

Pagina 25 - Normally Closed (NC)

InfraStruXure 20kW System: Installation, Operation, and Maintenance 25System Start-UpSafetys1. Set the System Enable switch to OFF, and then set the D

Pagina 26

26 InfraStruXure 20kW System: Installation, Operation, and MaintenanceStart-Up Procedure1. Set the upstream utility breaker to ON. 2. Ensure A-B-C clo

Pagina 27

System Start-Up: Start-Up ProcedureInfraStruXure 20kW System: Installation, Operation, and Maintenance 275. Install at least one power module in the I

Pagina 28

System Start-Up: Start-Up Procedure28 InfraStruXure 20kW System: Installation, Operation, and Maintenance7. Set the DC Disconnect breaker to ON, and t

Pagina 29

System Start-Up: Start-Up ProcedureInfraStruXure 20kW System: Installation, Operation, and Maintenance 29Apply power to load equipment1. Set the Q2 sw

Pagina 31 - System Start-Up

InfraStruXure 20kW System: Installation, Operation, and Maintenance 31Quick ConfigurationNetwork Management CardOverviewYou must configure the followi

Pagina 32 - Start-Up Procedure

32 InfraStruXure 20kW System: Installation, Operation, and MaintenanceInfraStruXure 20kW System Display InterfaceConfiguring network settings using th

Pagina 33

InfraStruXure 20kW System: Installation, Operation, and Maintenance 33APC Management Card WizardYou can use the APC Management Card Wizard at a Window

Pagina 34 - Control Menu

ii InfraStruXure 20kW System—Installation, Operation, and MaintenanceInstallation...

Pagina 35 - Apply power to load equipment

34 InfraStruXure 20kW System: Installation, Operation, and MaintenanceBOOTP & DHCP ConfigurationThe Boot Mode setting, a TCP/IP option in the syst

Pagina 36

Quick Configuration: BOOTP & DHCP ConfigurationInfraStruXure 20kW System: Installation, Operation, and Maintenance 35DHCPYou can use a RFC2131/RFC

Pagina 37 - Quick Configuration

36 InfraStruXure 20kW System: Installation, Operation, and MaintenanceControl ConsoleLocal access to the control consoleYou can use a local computer,

Pagina 38 - Interface

Quick Configuration: Control ConsoleInfraStruXure 20kW System: Installation, Operation, and Maintenance 372. Use Ping with a size of 113 bytes to assi

Pagina 39 - APC Management Card Wizard

38 InfraStruXure 20kW System: Installation, Operation, and MaintenanceHow to Access a Configured InfraStruXure 20kW SystemOverviewOnce the Management

Pagina 40

InfraStruXure 20kW System: Installation, Operation, and Maintenance 39OperationDisplay InterfaceYou can use the display interface to configure setting

Pagina 41 - 04) is the length

Operation: Display Interface40 InfraStruXure 20kW System: Installation, Operation, and MaintenanceNavigating screensFrom any screen, you can press the

Pagina 42 - Control Console

Operation: Display InterfaceInfraStruXure 20kW System: Installation, Operation, and Maintenance 41Top-Level Status screenAfter the display interface h

Pagina 43 - IP address. For example:

Operation: Display Interface42 InfraStruXure 20kW System: Installation, Operation, and MaintenanceControl screenFrom the Control screen, you can selec

Pagina 44 - 20kW System

Operation: Display InterfaceInfraStruXure 20kW System: Installation, Operation, and Maintenance 43Setup screenFrom the Setup screen, you can select th

Pagina 45 - Operation

InfraStruXure 20kW System—Installation, Operation, and Maintenance iiiControl Console. . . . . . . . . . . . . . . . . . . . . . . .

Pagina 46 - Navigating screens

Operation: Display Interface44 InfraStruXure 20kW System: Installation, Operation, and MaintenanceAccessories screenThe Accessories screen is used onl

Pagina 47 - Top-Level Menu screen

Operation: Display InterfaceInfraStruXure 20kW System: Installation, Operation, and Maintenance 45Logging screensThe Logging screen allows you to cust

Pagina 48 - Status screens

Operation: Display Interface46 InfraStruXure 20kW System: Installation, Operation, and MaintenanceDiags screensThe Diagnostics screen provides informa

Pagina 49 - Setup screen

InfraStruXure 20kW System: Installation, Operation, and Maintenance 47ProceduresHow to transfer the InfraStruXure 20kW System UPS into maintenance byp

Pagina 50 - Accessories screen

Operation: Procedures48 InfraStruXure 20kW System: Installation, Operation, and Maintenance2. Turn ON the Q3 switch.NoteThe H2 LED above the Q2 switch

Pagina 51 - NTER key to view a

Operation: ProceduresInfraStruXure 20kW System: Installation, Operation, and Maintenance 49The UPS is now in maintenance bypass operation.5. If applic

Pagina 52 - NTER key. Then press the

Operation: Procedures50 InfraStruXure 20kW System: Installation, Operation, and MaintenanceHow to return from maintenance bypass operation1. Turn ON t

Pagina 53 - Procedures

Operation: ProceduresInfraStruXure 20kW System: Installation, Operation, and Maintenance 51c. Select Turn UPS Output On from the Control menu, and pre

Pagina 54 - Operation: Procedures

Operation: Procedures52 InfraStruXure 20kW System: Installation, Operation, and MaintenanceNoteThe H2 LED above the Q2 switch illuminates, indicating

Pagina 55 - 6. Turn OFF the Q1 switch

Operation: ProceduresInfraStruXure 20kW System: Installation, Operation, and Maintenance 53How to ensure total power off1. Command the UPS to turn off

Pagina 56

iv InfraStruXure 20kW System—Installation, Operation, and MaintenanceMaintenance ...

Pagina 57

Operation: Procedures54 InfraStruXure 20kW System: Installation, Operation, and Maintenance3. If applicable, set the XR Battery Enclosure DC Disconnec

Pagina 58

InfraStruXure 20kW System: Installation, Operation, and Maintenance 55TroubleshootingOverviewThis section lists all of the alarm and status messages t

Pagina 59 - How to ensure total power off

56 InfraStruXure 20kW System: Installation, Operation, and MaintenanceAlarm Messages on the Display InterfaceGeneral statusDisplay message Meaning Cor

Pagina 60

Troubleshooting: Alarm Messages on the Display InterfaceInfraStruXure 20kW System: Installation, Operation, and Maintenance 57Battery Module Quantity

Pagina 61 - Troubleshooting

Troubleshooting: Alarm Messages on the Display Interface58 InfraStruXure 20kW System: Installation, Operation, and MaintenanceGeneral faultExternal sw

Pagina 62 - General status

Troubleshooting: Alarm Messages on the Display InterfaceInfraStruXure 20kW System: Installation, Operation, and Maintenance 59Internal Communica-tions

Pagina 63

Troubleshooting: Alarm Messages on the Display Interface60 InfraStruXure 20kW System: Installation, Operation, and MaintenanceModule failureThreshold

Pagina 64 - General fault

Troubleshooting: Alarm Messages on the Display InterfaceInfraStruXure 20kW System: Installation, Operation, and Maintenance 61Runtime Is Below Alarm T

Pagina 65 - Check that all power mod

Troubleshooting: Alarm Messages on the Display Interface62 InfraStruXure 20kW System: Installation, Operation, and MaintenanceBypassDisplay message Me

Pagina 66 - Threshold alarm

InfraStruXure 20kW System: Installation, Operation, and Maintenance 63MaintenanceParts ReplacementYou can replace power modules, battery units, commun

Pagina 67

InfraStruXure 20kW System—Installation, Operation, and Maintenance 1SafetyOverviewSafety symbols used in this guideSAVE THESE INSTRUCTIONS. This manua

Pagina 68

Maintenance: Parts Replacement64 InfraStruXure 20kW System: Installation, Operation, and MaintenanceHow to return parts to APCCall APC Customer Suppor

Pagina 69 - Maintenance

Maintenance: Parts ReplacementInfraStruXure 20kW System: Installation, Operation, and Maintenance 65How to remove a power module1. To deactivate the p

Pagina 70 - Replacement parts

Maintenance: Parts Replacement66 InfraStruXure 20kW System: Installation, Operation, and MaintenanceHow to install a power module1. With one person po

Pagina 71 - How to remove a power module

Maintenance: Parts ReplacementInfraStruXure 20kW System: Installation, Operation, and Maintenance 67How to install an intelligence module1. Carefully

Pagina 72 - How to install a power module

Maintenance: Parts Replacement68 InfraStruXure 20kW System: Installation, Operation, and MaintenanceBattery replacementIf a battery unit fails less th

Pagina 73 - How to install a card

InfraStruXure 20kW System: Installation, Operation, and Maintenance 69Adding PartsParts available from APCAPC SmartSlot CardsAP9607 2-Port Interface E

Pagina 74 - Battery replacement

Maintenance: Adding Parts70 InfraStruXure 20kW System: Installation, Operation, and MaintenanceHow to add circuit breakers and power cablesAdd a circu

Pagina 75 - Adding Parts

Maintenance: Adding PartsInfraStruXure 20kW System: Installation, Operation, and Maintenance 71Remove the wiring access cover. In order to attach powe

Pagina 76 - Add a circuit breaker

Maintenance: Adding Parts72 InfraStruXure 20kW System: Installation, Operation, and MaintenanceConnect the power cable wires. 1. At the back of the pa

Pagina 77 - Add a power cable

InfraStruXure 20kW System: Installation, Operation, and Maintenance 73Upgrading FirmwareYou can download firmware updates or language versions to the

Pagina 78 - Maintenance: Adding Parts

2 InfraStruXure 20kW System—Installation, Operation, and MaintenanceWarningsReceiving/movingDo not tilt the InfraStruXure 20kW System greater than 45°

Pagina 80

InfraStruXure 20kW System: Installation, Operation, and Maintenance 75SpecificationsInfraStruXure 20kW SystemPerformanceEfficiencyAC–AC at nominal mai

Pagina 81 - Specifications

Specifications: InfraStruXure 20kW System76 InfraStruXure 20kW System: Installation, Operation, and MaintenanceInputInput CurrentNormal 61.3A Current

Pagina 82

Specifications: InfraStruXure 20kW SystemInfraStruXure 20kW System: Installation, Operation, and Maintenance 77Runtime8 minutesTwo battery shelves: @

Pagina 83

Specifications: InfraStruXure 20kW System78 InfraStruXure 20kW System: Installation, Operation, and MaintenancePhysicalDimensionsHeight 81.5in (2068mm

Pagina 84

Specifications: InfraStruXure 20kW SystemInfraStruXure 20kW System: Installation, Operation, and Maintenance 79Communication and ManagementInterface p

Pagina 85

Specifications: InfraStruXure 20kW System80 InfraStruXure 20kW System: Installation, Operation, and MaintenanceSystem DC Input Protection Condition: T

Pagina 86

InfraStruXure 20kW System: Installation, Operation, and Maintenance 81Product InformationWarrantyInfraStruXure standard warrantyThe InfraStruXureTM sy

Pagina 87 - Product Information

82 InfraStruXure 20kW System: Installation, Operation, and MaintenanceLife-Support PolicyAPC three-phase systemsAmerican Power Conversion Corporation

Pagina 88 - APC three-phase systems

InfraStruXure 20kW System: Installation, Operation, and Maintenance 83How to Obtain ServiceObtaining serviceTo obtain support for problems with your I

Pagina 89 - Obtaining service

Safety: WarningsInfraStruXure 20kW System—Installation, Operation, and Maintenance 3Adding power cables and circuit breakersThe APC InfraStruXure Buil